Skip to main content

What We Do

Home Construction Projects

Here's the latest from our construction sites!

 

 

Brentwood Road Updates

March 4, 2020 - The Moore family will be given the key to their new home!  Congratulations to them and to all who helped make their dream come true!

As of January 22, 2020 - The house looked SO AWESOME for the dedication on the 12th, but finishing touches and cleanup and yard work continue, even during the week.  Feel free to stop by and lend a hand so the family can move in next month!

Dec 28 2019 - Jan 4, 2020 - Flooring, appliances and counter tops are installed and we will have a Dedication on January 12th!

The Three Amigos

Dec 21, 2019 - 

  • Kitchen cabinets are fully installed, thanks to Boston Kitchen Designs; 
  • Granite counter tops are 90% installed, thanks to The Granite Guys; 
  • Hardwood floors are 75% installed; 
  • Bathrooms tiled floors are 50% installed; 
  • Interior painting is 90% complete;
  • Septic System: 100% complete thanks to Watson Excavation.

SAVE THE DATE:  Dedication ceremony Sunday, January 12th

 Dec 10-11, 2019 -  Joel Stern from Boston Kitchen Designs donated his time on Dec. 10th and 11th to install the cabinets at Brentwood Road in Kingston. With his generous assistance, we are one step closer to completing the finish work on this home. 

Joel Stern, Boston Kitchen Designs

Joel Stern, Boston Kitchen Designs

Dec 7, 2019 - Moving right along!

  • Interior painting                80% complete
  • Interior doors and trim DONE.  THANKS to Dave & Taylor Berry and a volunteer crew from GHV Carpenters Inc
  • Oak stairway                    Done
  • Interior oak flooring        50% complete
  • Septic system                   90% complete

Nov 26, 2019 - Significant strides have been made  toward completing the home in Kingston!  Interior painting is now finished thanks to the Nov. 26th Painting Party. We are getting closer to turning over the keys to Hakeem and his family! 

Thanks to all who showed up for the Paint Party!!

Nov 16 - 22, 2019 - 100% vented soffit completed on the porch; 100% skim coating interior walls; 75% back-filled the septic system; 100% primed interior walls and ceilings.  Paint Party Tuesday, the 26th!

Long Pond Updates

As of February 29, 2020 -

     863:  Completed:  Siding, basement floor insulation;  80% completed:  Rough electric; Next to be done:  Rough plumbing and concrete poured for basement floor
     865:  Completed:  Siding; 80% completed:  Rough electric; 75% Complete:  Rough plumbing; Next up:  Basement insulation and concrete poured
     867:  Completed:  Interior partitions, lally columns, basement floor insulation, Exterior doors and windows installed; !0% Complete:  Vinyl siding; Ready for:Basement floor concrete, Rough plumbing and electric.

Dec 28, 2019 - Jan 4, 2020 -

     863:  Roofing completed by Viola, front porch footings in place, Vinyl siding 75% complete
     865:  Roofing completed by Viola, front porch footings in place
     867:  Azek trim delivered.  The porch roof is next.

Dec 21, 2019 -

   863:  Windows: 100% installed; Exterior doors: 50% installed; Porch roof: 100% constructed; Vinyl siding: 50% complete; Tubs & Showers: delivered thanks to Sagamore Plumbing; Septic System: 100% installed thanks to Bolduc Sanitation & Excavation

   865:  Windows: 50% installed; Porch roof: 100% constructed; Tubs & Showers: delivered thanks to Sagamore Plumbing; Septic System: 100% installed thanks to Bolduc Sanitation & Excavation

   867:  Roof Rafters: 100% installed; Roof plywood: 75% installed - Big thanks to BrownBuilt Inc.;Septic System: 100% installed thanks to Bolduc Sanitation & Excavation

Dec 18, 2019 - Thanks to our friends at Buzzards Bay Area Habitat for Humanity for referring a hardworking group from Travelers Insurance (W. Bridgewater office) who helped at our Long Pond Rd. sites where they made great progress on the important task of installing windows.

Crew from Travelers Ins, West Bridgewater

Dec 7, 2019 - Neither holiday weekends or bitter cold deters our volunteers from getting the job done!

     863:  Front Porch Roof Done; Roof trim Done; Vinyl siding 25%

     865:  Front Porch Roof 50%; Roof Trim 70%; Vinyl siding 20%
 

Nov 16, 2019 - A group from Church of the Pilgrimage joined in the fun and helped to bring the homes to this status:

     863:  75% roof trimmed; 90% interior partitions;20% vinyl siding installed

     865:  75% roof trimmed; bulkhead installed; 90% interior partitions; Started vinyl siding

     867:  60% of interior partitions completed.



More volunteers are welcome and encouraged to jump in on the building of both the Brentwood and Long Pond builds!
If interested, please visit our volunteer page here!
Thank you to our generous sponsors!
© 2020 Habitat for Humanity of Greater Plymouth

Powered by Firespring