Ground Breaking Ceremony was held April 13, 2008
138 Grove Street, Kingston
The Kingston community came out to celebration the groundbreaking for the second home to be built in Kingston. The ceremony had local who will speak on the beginning of the Womens' Build for the Silvia family. There was local clergy conducting the prayer to bless the ground the home to be built followed by a groundbreaking ceremony at the ceremony.
Our Current Plymouth Build
Work on our energy efficient home in Plymouth is nearly complete. In September we laid the foundation using Insulated Concrete Forms and concrete mixed with fly ash. Fly ash use improves concrete performance, making it stronger, more durable, and more resistant to chemical attack. Fly ash use also creates significant benefits for our environment. Supervision of the work on the foundation was performed by Tim Lyden of Fortress Green Building Supply.
We are hoping to complete the construction of this second home in Plymouth by the end of June 2008.
| Braley Lane Construction Schedule |
|
|
April 12
|
finish siding, start sheetrock
|
| April 19
|
sheetrock
|
|
April 26 | finish sheetrock, start interior trim arting vinyl siding |
| May 3 | interior trim |